Project Description
🟧 Short Project Description

🟧 Project Location
🟧 Project Characteristics
(main structural material)
🟧 Project Size
! If the project concerns renovation/extension, the fields Building, Number of Floors and Number of Basements refer only to the space under renovation/extension
(covered areas)
(ground plus upper floors)
🟧 Additional Project Details
(excluding VAT)
If you are not sure of the postcode you can look it up here
Image Image
Conditions & Requirements
🟧 This Project is open to tenders only from Contractors that meet the following requirements:
1. Obligatory Contractor Characteristics
(similar in terms of «Project Type», e.g. house, and in terms of «Construction Type», e.g concrete)
2. Contractor Commitments towards Project Owner
🟧 Special Notes of Owner/Consultant for the Attention of Contractors
🟧 Electrical – Mechanical Works
Plans & Documents

For this project, the following documents are available:
The documents are available only in digital form !

File NameDate UploadedLanguageDetailsActions
1. Architectural Plans (1 files) 
2. Structural / Civil Engineering Plans (2 files) 
3. Bill of Quantities (1 files) 
4. Electrical Plans (2 files) 
5. Mechanical Plans (1 files) 
6. Topographical Plan (1 files) 
7. Other Plans, Documents, Pictures (4 files) 
🟧 Contact Details of Project Owner/Consultant
Project Owner
Project Architect
Tenders Table
🟧 The Project has expired. The range of tenders given* is:
Tenders Comparison Table
Unlock the table amounts now and get a clear view of true market prices!
20 +VAT
Lowest Highest
(hidden) (hidden)
#Bill of Quantities (€ excl. V.A.T)Offer 1Offer 2Offer 3**
1Preliminaries25.150,0020.200,009.600,004%
2Earthworks3.002,005.000,003.874,001%
3Concrete, Formwork, Rebar in Concrete, Waterproofing24.209,0021.025,2522.570,304%
4Concrete, Formwork, Rebar in Concrete11.495,0012.830,7513.023,502%
5Structural Steelwork94.223,0065.753,7075.475,0015%
6Dry Works62.419,0042.296,0031.375,009%
7Substrates, Waterproofing21.538,0019.706,0029.968,005%
8Plumbing Works1.162,00764,50986,000%
9Flooring, Sills, Substrates, Thresholds34.234,0033.733,0026.809,506%
10Coverings, Thermal Insulations30.663,0022.080,0028.214,005%
11Dry Works17.128,0018.343,0013.431,003%
12Paintworks12.969,007.664,0010.279,502%
13External Sewerage5.518,005.702,006.526,001%
14External Works46.496,0039.571,2533.713,508%
15Builders' Assistance, General Assistance5.300,0015.400,002.800,002%
16Provisional Sums175.600,00175.600,00175.600,0034%
 Adjustment +/-0,00-669,45-3.245,300%
 Total571.106,00505.000,00481.000,00100%
 Price per m² (for 258 m²)2.2141.9571.864 
#Unit Prices for Indicative Works (excl. V.A.T)Offer 1Offer 2Offer 3
1Purchase of Construction Contract P/LS/MC(1) from MEDSK (€)1.050,001.400,001.100,00
2Construction Site Management Personnel (€)3.000,002.000,001.200,00
3Work Scaffolding (€)5.600,003.000,001.200,00
4Contractors All Risks Insurance (€)1.800,00800,00700,00
5General Excavation in Semi-hard Soil (€/m3)6,0016,006,00
6General Backfilling with Crusher-run (€/m3)31,0020,0028,00
7Transport of Excavated Materials Off-Site (€/m3)4,509,0010,00
8Concrete C12/15 for Blinding Layer (€/m3)100,0098,0090,00
9Concrete C30/37 with Crystalline Admixture for Raft Foundation (€/m3)140,00110,00120,00
10Rebar in Concrete B500C (€/Kg)1,201,351,30
11Rebar in Concrete Y10/200 with A393 Mesh (€/m2)11,0012,0015,00
12Waterproofing with 3 Coats of Bituminous Emulsion on Foundations (€/m2)7,004,508,00
13Concrete C30/37 for Slabs (€/m3)130,00115,00125,00
14Formwork for Fair-Faced Board-Marked Columns (€/m2)85,0055,0019,00
15Structural Steelwork SHS 100 x 100 x 3 (S275), incl. Flanges (€/Kg)6,093,503,87
16Structural Steelwork HEA 180 (S275), incl. Flanges (€/Kg)4,692,443,83
17Structural Steelwork IPE 160 (S275), incl. Flanges (€/Kg)4,112,653,86
18Polyurethane Panels 100mm Thick (€/m2)68,0035,0042,00
19Plasterboards 12,5mm in 2 Layers on Each 100mm Wall Side with Rockwool 50mm (50Kg/m3) (€/m2)73,0042,0055,00
20Concrete C20/25 for Substrate (€/m3)180,00270,00180,00
21Waterproofing with 2 Layers of 4mm-thick Bituminous Membrane (€/m2)32,0025,0019,00
22Waterproofing with Cementitious Mortar and Fiberglass Mesh (€/m2)22,0018,0012,00
23Downpipes PCV 75mm in Vertical Structural Elements (€/m)20,0012,5018,00
24Lightweight Concrete 600Kg/m3 for Substrate (€/m3)120,00180,0014,50
25Installation of Ceramic Tiles with Cement-Based Adhesive on Floors (€/m2)35,0025,0027,00
26Thermal Insulation of Facades with 80mm Expanded Polystyrene and Silicone Finish (€/m2)56,0066,0055,00
27Plasterboard 12,5mm for Internal Suspended Ceiling (€/m2)34,0040,0031,00
28Spatoula 2 Coats and Paint 3 Coats on Interior Plasterboards (€/m2)15,009,0012,00
29Waterproofing with 2 Layers Siloxane Water Repellent Impregnation for Exposed Concrete (€/m2)10,005,008,00
30Pavement with 50mm Slabs and Concrete Base (€/m2)32,0030,0045,00
31Pavement Curbs and Concrete Base (€/m)35,0025,00110,00
* The amounts result from the tenders uploaded by the bidding Contractors on Projects.cy. Projects.cy does not check the tenders for any errors or omissions; this is done at a later stage by the project Consultant.