| 1 | Purchase of Construction Contract P/LS/MC(1) from MEDSK (€) | 1.050,00 | 1.400,00 | 1.100,00 |
| 2 | Construction Site Management Personnel (€) | 3.000,00 | 2.000,00 | 1.200,00 |
| 3 | Work Scaffolding (€) | 5.600,00 | 3.000,00 | 1.200,00 |
| 4 | Contractors All Risks Insurance (€) | 1.800,00 | 800,00 | 700,00 |
| 5 | General Excavation in Semi-hard Soil (€/m3) | 6,00 | 16,00 | 6,00 |
| 6 | General Backfilling with Crusher-run (€/m3) | 31,00 | 20,00 | 28,00 |
| 7 | Transport of Excavated Materials Off-Site (€/m3) | 4,50 | 9,00 | 10,00 |
| 8 | Concrete C12/15 for Blinding Layer (€/m3) | 100,00 | 98,00 | 90,00 |
| 9 | Concrete C30/37 with Crystalline Admixture for Raft Foundation (€/m3) | 140,00 | 110,00 | 120,00 |
| 10 | Rebar in Concrete B500C (€/Kg) | 1,20 | 1,35 | 1,30 |
| 11 | Rebar in Concrete Y10/200 with A393 Mesh (€/m2) | 11,00 | 12,00 | 15,00 |
| 12 | Waterproofing with 3 Coats of Bituminous Emulsion on Foundations (€/m2) | 7,00 | 4,50 | 8,00 |
| 13 | Concrete C30/37 for Slabs (€/m3) | 130,00 | 115,00 | 125,00 |
| 14 | Formwork for Fair-Faced Board-Marked Columns (€/m2) | 85,00 | 55,00 | 19,00 |
| 15 | Structural Steelwork SHS 100 x 100 x 3 (S275), incl. Flanges (€/Kg) | 6,09 | 3,50 | 3,87 |
| 16 | Structural Steelwork HEA 180 (S275), incl. Flanges (€/Kg) | 4,69 | 2,44 | 3,83 |
| 17 | Structural Steelwork IPE 160 (S275), incl. Flanges (€/Kg) | 4,11 | 2,65 | 3,86 |
| 18 | Polyurethane Panels 100mm Thick (€/m2) | 68,00 | 35,00 | 42,00 |
| 19 | Plasterboards 12,5mm in 2 Layers on Each 100mm Wall Side with Rockwool 50mm (50Kg/m3) (€/m2) | 73,00 | 42,00 | 55,00 |
| 20 | Concrete C20/25 for Substrate (€/m3) | 180,00 | 270,00 | 180,00 |
| 21 | Waterproofing with 2 Layers of 4mm-thick Bituminous Membrane (€/m2) | 32,00 | 25,00 | 19,00 |
| 22 | Waterproofing with Cementitious Mortar and Fiberglass Mesh (€/m2) | 22,00 | 18,00 | 12,00 |
| 23 | Downpipes PCV 75mm in Vertical Structural Elements (€/m) | 20,00 | 12,50 | 18,00 |
| 24 | Lightweight Concrete 600Kg/m3 for Substrate (€/m3) | 120,00 | 180,00 | 14,50 |
| 25 | Installation of Ceramic Tiles with Cement-Based Adhesive on Floors (€/m2) | 35,00 | 25,00 | 27,00 |
| 26 | Thermal Insulation of Facades with 80mm Expanded Polystyrene and Silicone Finish (€/m2) | 56,00 | 66,00 | 55,00 |
| 27 | Plasterboard 12,5mm for Internal Suspended Ceiling (€/m2) | 34,00 | 40,00 | 31,00 |
| 28 | Spatoula 2 Coats and Paint 3 Coats on Interior Plasterboards (€/m2) | 15,00 | 9,00 | 12,00 |
| 29 | Waterproofing with 2 Layers Siloxane Water Repellent Impregnation for Exposed Concrete (€/m2) | 10,00 | 5,00 | 8,00 |
| 30 | Pavement with 50mm Slabs and Concrete Base (€/m2) | 32,00 | 30,00 | 45,00 |
| 31 | Pavement Curbs and Concrete Base (€/m) | 35,00 | 25,00 | 110,00 |